This project included the design, supply and installation of a 1,700m² tablet manufacturing facility and class 10,000 laboratory including a number of class 100 rooms.
Project Details
Project Name
Bausch & Lomb
Project Location
Waterford, Ireland
Project Size
3,000 m²
Project Value
€2 million
Project Duration
6 months
Cleanroom Classification
BSL 2
Project Overview
Bausch & Lomb
Provided by Asgard
Products & Services
Ceilings
1,700m² of fully flush long-span walk-on plank ceiling panels.
Partitions
3,000m² of metal faced fully flush FM approved paneling 50mm thick.
Furniture
Design, manufacture and installation of an integrated step-over bench.
Doorsets
Provision of approx 60 fully flush non rated doorsets and 15 fire rated units.
Interlocking
Design, supply, installation and commissioning of interlocking to 16 doorsets including a 7 door arrangement.
Structural
Design, supply and installation of a subgrid structure above entire ceiling including integrated handrails to the perimeter.
Miscellaneous
Work included 6 pass-through hatches which are electrically interlocked.