MSD’s vision is to make a difference to people’s lives by bringing innovative healthcare to those who need it most. This project was to three buildings, one being 3 stories high, total size of 1600m². The project included a high spec cleanrooms envelope, HEPA housings, automated sliding doors, rapid roller doors, interlocking etc.
Project Details
Project Name
Project Lion
Project Location
Brinny, Cork, Ireland
Project Size
1700m²
Project Value
€3.2 million
Project Duration
18 months
Architect
PM Group
Engineer
PM Group
Main Contractor
PM Group
Design Completed Using
Autocad 2D, Revit, Navisworks
Cleanroom Classification
BSL 2, ISO 7-8
Project Overview


MSD
Provided by Asgard
Products & Services
Ceilings
A combination of walk on ceiling (2.5 Kn 75 mm thick) including bulkheads Integrated electrical raceways & Cleanroom metal grid ceiling comprising of HPL ceiling tiles.
Partitions
550 linear metres of 50mm thick aluminium honeycomb panels ranging in heights from 3m to 5m including glazing etc & the construction of airwalls throughout the project as required.
Doorsets
Provision of swing doors & automated sliding doors.
Electrical
Design, supply and installation of walk-on lights emergency exit signs, sockets switches and automation.
Bumprails
Provision of bollard & wall mounted stainless steel bumprails.
Furniture
Design, supply and installation of furniture including, stainless steel, Trespa, and free standing office furniture.
Interlocking
Design, supply, installation & commissioning of interlocking systems.
HVAC
Design, supply and installation of terminal HEPA housings, low level air return walls, low level extract ducts, supply grilles and air monitoring.